cruise terminal 2 & terminal 4 parking deck expansion and roadway improvements project
The new construction of 1,818-space parking garage structure west of Terminal 4 in the Northport area of Port Everglades.
Schedule | Start Date | End Date |
---|---|---|
Design | January 2017 | September 2018 |
Construction | March 2019 | Fall 2020 |
(August 2020)
(August 2020)
An elevated walkway with moving sidewalks connects the Heron Parking Garage with Cruise Terminal 2 (October 18, 2020)