Cruise Terminal 2 & Terminal 4 Parking Deck Expansion and Roadway Improvements Project

The new construction of 1,818-space parking garage structure west of Terminal 4 in the Northport area of Port Everglades.

Schedule Start Date End Date
  Design   January 2017   September 2018
  Construction   March 2019   Fall 2020

Construction nearly completed on new Heron Parking Garage

(August 2020)

Construction on the new 1,818 space Heron Parking Garage

(August 2020)

An elevated walkway connects the Heron Parking Garage with Cruise Terminal 4.

An elevated walkway with moving sidewalks connects the Heron Parking Garage with Cruise Terminal 2 (October 18, 2020)